Overview
Key Project
Details
Status
under-development
Location
Bouldercombe, Queensland
Technology: BESS
1200
MWh
Energy production
300
MW
Operational Capacity
Project Approvals
The relevant assessments required as part of a Development Approval application for the proposed project are currently underway, this includes the following key focus areas:
- Stormwater assessment
- Environmental noise assessment
- Preliminary fire risk assessment, and
- Environmental assessment.
Potentia Energy intends to lodge a Development Approval application with the Rockhampton Regional Council Government in due course.
Project Timeline
Late 2024
Target Development Approval application lodgement
Target for lodgement of the Development Approval application to the Rockhampton Shire Council.
Late 2026
Targeted commencement of construction
Subject to obtaining the necessary approvals, targeted commencement of construction at the Capricorn BESS site.
Mid 2028
Targeted completion of the construction
Subject to obtaining the necessary approvals, targeted completion of construction phase for the Capricorn BESS.
Community Survey
As part of our approach to community engagement for the project, we are seeking feedback from the community, to better understand local values and priorities and inform planning for potential initiatives to be undertaken within the local area close to the Capricorn BESS Project site. The survey results will inform local community benefit sharing initiatives, where feasible and aligned with the company values, policies and capabilities. We appreciate local community members time to contribute to the survey. If you would like to discuss your feedback in further details, please contact us.