The Tallawang Solar Hybrid Project is located approximately 8 km Northwest of Gulgong in New South Wales. The project will comprise of the construction and operation of a 500 megawatt (MW) Solar Farm and a 500 MW/1000 MWh Battery Energy Storage System and, related civil and electrical infrastructure.  

The project is targeted to commence pre-construction activities in 2026, with construction activities targeted to start in 2027, and operations due to begin in 2030. 

Key Project
Details

Status under-development Location Tallawang, NSW Solar and BESS Technology: Solar & BESS 1300 GWh Energy production 500 MW Operational Capacity Over 250,000+ New South Wales homes

Project Approvals

The Tallawang Solar Hybrid project is approved as a State Significant Development in accordance with Environmental Planning Assessment Act 1979. 

The Approvals set out conditions that must be complied with in undertaking the development. The conditions cover construction, operation, decommissioning, and administrative matters. 

All related planning and approvals documentation is available at the NSW Major Projects Register here, and at the Independent Planning Commission website here. 

Project Timeline

2021

Project development and planning

The project was originally initiated and progressed through planning by RES, who acted as the proponent during the early development phase.

2022

Submission of Development Application

A Development Application for Tallawang Solar Farm as State Significant Development, in accordance with Environmental Planning and Assessment Act 1979, was submitted to the NSW Department of Planning and Environment (DPE).

2024

Project acquisition

Tallawang Solar Hybrid Farm was acquired by Potentia Energy in mid 2024. Potentia Energy commenced working closely with RES to continue the development of the project and ensure a smooth transition for local community stakeholders.

2025

Development Approval

In July 2025, the project was referred for determination to the NSW Independent Planning Commission (IPC) by the NSW Department of Planning, Housing and Infrastructure (DPHI).

In October 2025, the IPC determined to grant consent to the project’s Development Application.

2027

Target commencement of construction

2030

Target commencement of operations

Project Resources

Contact Us

This field is for validation purposes and should be left unchanged.
Terms and Conditions(Required)
*Mandatory Fields
This field is hidden when viewing the form

Project Contact

Giulia Scataglini Community Engagement and Sustainability Specialist

0419 668 522 

Explore more projects

view all projects